The Massachusetts Department of Energy Resources (DOER) recently
unveiled new emergency regulations that double the capacity of the
state's solar incentive program and provide important relief to
projects under development in light of the COVID-19
pandemic.
Following various Massachusetts electric companies issuing blanket notices of force majeure under the
standards for interconnection of distributed generation tariff over
the past several weeks, on April 15, 2020, the Massachusetts
Department of Energy Resources (DOER) issued an emergency regulation granting a six month
extension to the Reservation Period for all Solar Tariff
Generation Units (STGUs) in light of the COVID-19 pandemic.
Additionally, all STGUs that submit a new application to the DOER
between April 15, 2020 and July 1, 2020 will receive this automatic
six month extension at the time of application. In other
words, STGUs applying for a Statement of Qualification between
April 15 and July 1 of this