Level 10 Construction V. Sea World LLC: Can Force Majeure Save Sea World?

Sea World contracted with Level 10 in June 2019 to build what is believed to be the new Emperor Dive Coaster at the Sea World San Diego park.

United StatesCoronavirus (COVID-19)

On June 8, 2020, Level 10 Construction, LP ("Level 10"), a construction company hired by Sea World San Diego ("Sea World"), filed a Complaint in California federal court alleging that Sea World is withholding over $3.2 million dollars in payments from Level 10. In the Complaint, Level 10 alleged that Sea World has declined to issue payments until the Sea World park reopens. Sea World has remained closed since March 2020 due to COVID-19.

Sea World contracted with Level 10 in June 2019 to build what is believed to be the new Emperor Dive Coaster at the Sea World San Diego park. In its Complaint and a later Motion for Issuance of Writ of Attachment filed on June 25, 2020, Level 10 alleged that it completed all of its work necessary under the contract until Sea World asked Level 10 to stop its work on the project. Sea World also allegedly advised that it "would not process outstanding payments until the parks open." Level 10 maintained that under its contract with Sea

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from