COVID-19: Energy Project Financing Considerations

Globally, the coronavirus (COVID-19) has caused not only a major public health crisis but also major economic uncertainty, as supply chains are brought to a standstill, flights are grounded, borders...

United StatesCoronavirus (COVID-19)

HIGHLIGHTS


  • In the context of an energy project finance transaction, coronavirus-related interruptions to a project's construction or operations can have significant implications for project borrowers, sponsors, project counterparties and financiers.
  • This Holland & Knight alert outlines some of the issues that may arise under project finance documentation for a typical energy project finance transaction in light of the uncertainties and difficulties arising in the current environment.

Globally, the coronavirus (COVID-19) has caused not only a major public health crisis but also major economic uncertainty, as supply chains are brought to a standstill, flights are grounded, borders, businesses and schools are closed, "stay in place" orders are announced and financial markets remain volatile. In the context of an energy project finance transaction, COVID-19-related interruptions to a project's construction or operations can have significant implications for

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from