The closure of local recorders’ and county clerks’
offices in the wake of COVID-19, and the prospect of future
closures, has had a profound effect on commercial real estate
transactions. This is particularly true in New York where the
closures are preventing the filing of mechanics’ liens and
building loan contracts, in some cases preventing the commencement
of new construction projects.
With respect to on-going construction projects in New York,
current conditions likely will cause borrowers to seek
modifications to their existing building loan contracts. However,
Section 22 of New York Lien Law requires that any modification of a
building loan contract be filed within 10 days after the execution
of the modification along with an updated Section 22
Affidavit.1 If the modification is not filed within such
10 day period, a building loan mortgage may lose some or all of its
priority against later filed mechanic's
liens.2