Many a legal article has now been written concerning the relief
that contractors may be entitled to under the JCT suite of
contracts as a result of the COVID-19 pandemic with the general
position being that contractors are entitled to time but not money.
Notwithstanding this, there are certain nuances to the JCT
contract* that might perhaps best be at the back of a
developer's mind when managing its contractor in the shadow of
COVID-19.
A Contractor's Endeavour...
There has been uncertainty as to the extent of the
contractor's obligation under clause 2.25.6.1 of the JCT to use
its "best endeavours" to prevent delay to the progress of
the works during the COVID-19 outbreak. While it should be observed
that this does not translate to an obligation on contractors to
accelerate the Works to achieve the recovery of progress against
the programme at their own cost, it is a stringent obligation that
requires contractors to take all those steps in their power which
are