Force Majeure: General Assertions As To Impact Of Covid-19 And Brexit Not Sufficient To Defeat Summary Judgment Application

The High Court has entered summary judgment in favour of a port operator against a sea ferry operator for the payment of a shortfall due for a failure to meet minimum volumes.

United KingdomCoronavirus (COVID-19)

The High Court has entered summary judgment in favour of a port operator against a sea ferry operator for the payment of a shortfall due for a failure to meet minimum volumes. The court rejected an argument that the operator could rely on a force majeure defence in light of Brexit and the Covid-19 pandemic: PD Teesport Ltd v P&O North Sea Ferries Ltd [2023] EWHC 857 (Comm).

This decision is a useful reminder that, while the Covid-19 pandemic and/or Brexit may be categorised as force majeure events, whether a force majeure clause is triggered will depend on a close analysis of the wording of the clause. Where the clause requires specific conditions to be met, it will be insufficient to rely on broad assertions as to the impact of the Covid-19 pandemic and/or Brexit.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from