In two recent cases the High Court has considered the
contractual positions where sports competition organisers, due to
the COVID-19 pandemic, were unable to hold live events and were
therefore unable to provide their broadcast partners with
contractually agreed media rights.
This update illustrates how similar factual
circumstances can give rise to very different results depending on
the protections the parties were able to negotiate and agree at the
time they signed their contracts.
In the first case, the broadcaster successfully relied on a wide
force majeure clause. A force majeure clause is one which suspends
or excuses performance of contractual obligations because of the
occurrence of an identified event e.g. war, government
interference, industrial action or a global pandemic. Like any
other contractual clause the precise effect of a force majeure
clause will depend on its drafting, and the clause will be
construed by the Courts subject to the usual legal