On 23 June 2010, the Cabinet of Ministers of Ukraine (CMU) adopted a new yearly "Procedure for the Issuance of Special Permits for Subsoil Use in 2010" (the "Procedure").

UkraineEnvironment
Olexander Martinenko
Olexander Martinenko
Vitaliy Radchenko
Vitaliy Radchenko
Inna Saakova
Inna Saakova

On 23 June 2010, the Cabinet of Ministers of Ukraine (CMU) adopted a new yearly "Procedure for  the Issuance of Special Permits for Subsoil Use in 2010" (the "Procedure"). The regime introduced by CMU is much more lenient (in comparison to the respective procedure effective in 2009).

As a general rule, the Ministry of Environmental Protection is responsible for holding auctions to award these special permits to the wining bidders. However, the Procedure also permits other numerous grounds which would allow the special permits to be issued without the auction procedure. These include the following grounds:

  • for the production of natural resources in 2 cases. First, where the applicant had previously: (1) conducted a geological survey at a licensed area at its own expense, (2) performed an estimation of the reserves and (3) obtained approval from the State Commission on Reserves of the Mineral Resources. Second, if the respective estimation of the deposits is