ARTICLE · 22 APRIL 2020

COVID-19: Force Majeure Guidelines Published For Public Tender Contracts

The guidelines detail the procedures for contractors' force majeure notifications.

TurkeyCoronavirus (COVID-19)

The Presidency of the Republic of Turkey published force majeure guidelines for public tender contracts ("Guidelines") in the Official Gazette dated April 2, 2020, No. 31087. The guidelines detail the procedures for contractors' force majeure notifications.

What do the Guidelines say?

The Guidelines cover contracts executed under the Public Tender Law No. 4734 (along with its exceptions). The Guidelines indicate that an application should be made to the contracting authority documenting the impossibility of performance, if the performance of a contract is not possible due to the COVID-19 outbreak, temporarily or permanently, in part or in whole.

The contracting public authority will review these applications of impossibility of performance under Article 10 of the Public Tender Contract Law No. 4735, which regulates the circumstances for force majeure events and other regulations. The Guidelines also require contracting public authorities to consult with the

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.