The Presidency of the Republic of Turkey published force majeure
guidelines for public tender contracts
("Guidelines") in the Official Gazette
dated April 2, 2020, No. 31087. The guidelines detail the
procedures for contractors' force majeure notifications.
What do the Guidelines say?
The Guidelines cover contracts executed under the Public Tender
Law No. 4734 (along with its exceptions). The Guidelines indicate
that an application should be made to the contracting authority
documenting the impossibility of performance, if the performance of
a contract is not possible due to the COVID-19 outbreak,
temporarily or permanently, in part or in whole.
The contracting public authority will review these applications
of impossibility of performance under Article 10 of the Public
Tender Contract Law No. 4735, which regulates the circumstances for
force majeure events and other regulations. The Guidelines also
require contracting public authorities to consult with the