New Court Of Appeal Ruling Regarding The Requirements For The Contractor's Economic Supporting Documentation For ÄTA Work [Ändrings- Och Tilläggsarbeten – Alterations And Additional Work].

The contractor's economic supporting documentation for work including ÄTA work carried out according to the prime cost principle was examined in a recent ruling by the Court of Appeal.

SwedenLitigation, Mediation & Arbitration

The contractor's economic supporting documentation for work including ÄTA work carried out according to the prime cost principle was examined in a recent ruling by the Court of Appeal. The judgment stated that the contractor has an information advantage in relation to the client and the ability to secure supporting documentation for its claim on an ongoing basis, which is why the requirements for the contractor's evidence are set relatively high. This article briefly reports on the court case and on some additional considerations relating to the requirements a client can impose on the contractor's economic supporting documentation for ÄTA work.

The ÄTA work must be compensated through the prime cost principle (open account) if there is no unit price list, priced bill of quantities or other agreed charging norm and the parties do not agree on a fixed price (ABT 06/AB 04 Chapter 6, sections 6–7). In the case of work on an open account according to the prime cost

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from