COVID-19 Africa: Legal Considerations For Construction Site Closures

In this article we consider the issues parties to a construction contract should consider both before, and during, any site shut down.

South AfricaCoronavirus (COVID-19)

As governments across Sub-Saharan Africa introduce restrictions on movement and social interaction in an attempt to halt the spread of the COVID-19 virus, parties to infrastructure projects are facing increased pressure to close their construction sites where necessary. In this article we consider the issues parties to a construction contract should consider both before, and during, any site shut down.

Who should close the site?

Site closure is a drastic step for either party to a construction contract to take and so employers and contractors should carefully consider the contractual implications before instructing a site shut down.

Employer instructed shut down

Employers under a construction contract are often developers responsible for the overall project or the site owner. As a result, they may face increasing public or political pressure to close down their sites to reduce the spread of the virus, but employers should consider whether this may expose

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from