In Grace Electrical Engineering Pte Ltd v EQ Insurance Co Ltd [2016] SGHC 233, the plaintiff was the occupier of a factory unit. Grace Electrical was the insured under a public liability policy...

SingaporeInsurance

In Grace Electrical Engineering Pte Ltd v EQ Insurance Co Ltd [2016] SGHC 233, the plaintiff ("Grace Electrical") was the occupier of a factory unit. Grace Electrical was the insured under a public liability policy (the "Policy") issued by the defendant ("EQ Insurance") on 15 March 2012.

In the early hours of 6 September 2012, a fire started at the factory unit occupied by Grace Electrical, which spread to an adjoining factory united occupied by Te Deum Engineering Pte Ltd ("Te Deum"). In a separate case, the Singapore High Court found Grace Electrical liable in negligence for the fire damage to the unit occupied by Te Deum. In Grace Electrical, Grace Electrical sought an indemnity from EQ Insurance in respect of its liability to Te Deum.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from