The Scottish Courts have recently delivered some essential clarity on when the five-year prescription period for construction defect claims in Scotland begins, and on the narrow conditions...

ScotlandReal Estate and Construction

Introduction

The Scottish Courts have recently delivered some essential clarity on when the five-year prescription period for construction defect claims in Scotland begins, and on the narrow conditions under which it can be paused by section 6(4) of the Prescription and Limitation (Scotland) Act 1973. In summary, the Court confirmed that prescription begins at practical completion of the works, and strictly limits when the "saving provisions" under section 6(4) of the Prescription and Limitation (Scotland) Act 1973 can cure a time-barred claim.

The decision offers as stark guidance that accurate, up-to-date project records, and early issue-spotting are the best safeguards against parties potentially losing the right to recover for defects in Scotland.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from