Renewable energy deal discussions centered on projects in Puerto
Rico have been difficult – particularly for project owners
– over the past few years. The foundations of most of the
projects on the island were power purchase agreements (PPAs) with
PREPA, the utility which, as an organ of the government was capable
of issuing its own bonds and faced the same credit issues as the
island itself. Therefore most projects have teetered along on life
support for some time as financiers were unwilling to even open
discussions with such a poor credit offtaker in the mix. However,
interest in the island seems to have been heating up lately.
Proposals for behind-the-meter projects with private offtakers
and wheeling scenarios have been popping up. Even old PREPA deals,
many of which had died slow deaths in the wake of missed debt
payments, may be in the process of resurrection. Why? Some may have
missed it during the dog days of summer, but the main reason is the
passage of