The main purpose of the Construction Contracts Act 2002 is to facilitate regular and timely payments between parties.

New ZealandReal Estate and Construction

One of the main purposes of the Construction Contracts Act 2002 (Act) is to facilitate regular and timely payments between parties. The Act provides a standardised mechanism for dealing with payments through its payment claim and payment schedule regime. Amendments to the Act mean the payment claim and payment schedule regime applies to both residential and commercial building work. Therefore, it is more important than ever that the clients, contractors and subcontractors understand the requirements and consequences of payment claims and payment schedules.

Requirements of a payment claim

The requirements for a valid payment claim are set out in section 20(2) of the Act. A payment claim must:

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from