New NZS3910 contract - more than a chip off the old block

The new standard construction contract, NZS3910:2013, contains a new structure as well as other changes and new features.

New ZealandReal Estate and Construction

The new standard construction contract, NZS3910:2013, although the product of what was billed by the Standards Committee as a "limited technical review", contains a number of significant changes and new features.

On balance, we like it - but there is a lot for users to digest. Principals, in particular, will need to modify their standard amendments to reflect the changes.

Key changes

These include:

  • a new structure with the form of Contract Agreement now at the front of the document (formerly included as the Second Schedule)
  • new guidelines which no longer have contractual status
  • new provisions governing cost reimbursement contracts
  • a prohibition on assignment of the contract by either the Principal or the Contractor without the consent of the other party (such consent not to be unreasonably withheld or delayed)