Construction projects around the world rely on both a healthy
labour force and, increasingly, on materials and components that
are produced in another country; particularly those produced in
China.
Covid-19 has developed rapidly, slowing trade and disrupting the
international supply chain. Movement of people and goods has been
limited, meaning the ability to source materials will become an
issue. This raises some important issues in relation to
construction projects, particularly in relation to liability for
delay.
Effects on labour force
The human element of the build phase of the construction
contract is likely to be problematic and result in delays. As the
number of infections increases, there is a high likelihood that
labour will have to self-isolate which may lead to sites being shut
down, which will inevitably lead to delay and disruption to the
progress of construction works. In addition, PCBU's under the
Health and Safety at Work Act 2015 are obliged to