A recent decision from the Court of Appeal, Ebert
Construction Ltd v Sanson and Bridgman [2017] NZCA 239, will
reassure parties to construction contracts about the validity of a
type of three-way financing arrangement known as a "direct
agreement" (also known as direct payment agreements or
tripartite agreements). This is a three-way agreement between
developer, builder and financier. The agreement empowers the
financier to step in and complete the project if the developer
defaults, and may either permit or require the financier to make
payments directly to the builder during the ordinary life of the
project.
The agreements became popular in the 1990s, with financiers
wanting the "step in rights" that the agreements
typically provide, meaning that the builder could not immediately
terminate the construction contract if the developer defaulted on
its obligations. From a builder's point of view the direct
payment obligation from the financier would also provide