The importance of communicating clearly when choosing
whether to exercise a contractual election in a construction
contract has been reinforced by the Court of Appeal in a decision
which was welcomed by the subcontractor as "a win for the
little boys".
We look at the Court of Appeal judgment and reprise the history
of the
case.
Brief background
At issue was a disputed payment claim in relation to the
construction of a supermarket carpark in Christchurch. The claim
had been submitted by Siteworks to the head contractor (Watts &
Hughes) three days after its "Due Date" on the 25th of
the month.
Under clause 5(c) of the Master Builders Standard Form of
Subcontract, Watts & Hughes had a discretion to treat a late
payment claim as if it had been received on the 25th of the
following month (the next Due Date), postponing its obligation to
issue a payment schedule by a month.