Construction Contracts Act: retentions regime wilts under scrutiny in first court case

Article discusses case which exposed uncertainties arising from amendments to the Construction Contracts Act.

New ZealandReal Estate and Construction

The retentions regime, brought into effect on 1 April 2017 through an amendment to the Construction Contracts Act, wilted under the scrutiny of its first test in the Wellington High Court this month.

The Court had to struggle against "gaps in the legislation" and "imprecise language" as it sought to resolve issues which should have been resolved by the lawmakers – in particular, how, and by whom, retention monies should be allocated in a receivership.

Either we await the accumulation of case law to inject some much needed clarity into this regime, which will be a slow and expensive process, or the Government appoints an expert panel to review it and recommend improvements.

At issue

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The information in this article is for informative purposes only and should not be relied on as legal advice. Please contact Chapman Tripp for advice tailored to your situation.

See more popular content from