ARTICLE · 16 MARCH 2022

CCAs Sudden-death Regime For Construction Contracts

If a valid payment claim is issued & no payment schedule is received, the amount claimed becomes a due debt.

New ZealandReal Estate and Construction

Those in the construction industry will be familiar with the "sudden death" regime set out in the Construction Contracts Act 2002 (CCA). If a valid payment claim is issued and no payment schedule is received within the applicable timeframe, the amount claimed becomes a due debt.

The recent case of Nicholls Group Projects Ltd v Plan Design Build Homes Ltd [2022) NZHC 56 reiterates the importance of issuing of a payment schedule on time.

Nicholls Group Projects Ltd v Plan Design Build Homes Ltd

In this case, Plan Design Ltd (Plan Design) agreed to provide labourers for a building project managed by the Nicholls Group Project Ltd (Nicholls Group) (contract).

Plan Design issued four invoices for work it completed as payment claims under the CCA totalling $96,707.87. These were based on the contractually agreed price of $65 per hour for 5 builders. Nicholls Group did not provide a payment schedule in response. Plan Design then issued a statutory demand on the

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from