Share on LinkedInShare on LinkedIn

ARTICLE · 04 JULY 2007

Director´s Liability, Leaky Homes And The Tortious Duty Of Councils

In the recent "Leaky Homes" case of Dicks v Hobson Swan Construction Limted & Ors, Baragwanath J, HC Auckland, CIV 2004-404-1065, 22 December 2006, the High Court awarded Hobsonville homeowner Colleen Dicks a total of $250,900 to meet the cost of repairing her 12 year old house, to compensate her for three years of distress and to meet the costs of her expert witnesses ($29,684.43).

New ZealandLitigation, Mediation & Arbitration
Grant Slevin (Formerly With Wynn Williams Lawyers)
Grant Slevin (Formerly With Wynn Williams Lawyers)
Belinda Barclay (Formerly With Wynn Williams Lawyers)
Belinda Barclay (Formerly With Wynn Williams Lawyers)
Author LinkedIn connections

By Associate Belinda Barclay, and solicitor Grant Slevin, of the Christchurch Lawlink firm of Wynn Williams & Co.

In the recent "Leaky Homes" case of Dicks v Hobson Swan Construction Limted & Ors, Baragwanath J, HC Auckland, CIV 2004-404-1065, 22 December 2006, the High Court awarded Hobsonville homeowner Colleen Dicks a total of $250,900 to meet the cost of repairing her 12 year old house, to compensate her for three years of distress and to meet the costs of her expert witnesses ($29,684.43).

Judgment was entered against the building company, now in liquidation, its director in person and against Waitakere City Council. Because the builder and his company are unable to pay, the Waitakere City Council is left to bear the whole cost. There will be no appeal from the decision – a happy outcome for Mrs Dicks.