Consent applicants under the Resource Management Act (RMA), territorial authorities and other RMA decision-makers will welcome the clarity of process provided by the High Court’s ruling yesterday in relation to the Project Hayes wind farm.

New ZealandEnvironment
John Hassan
John Hassan
Suzanne Janissen
Suzanne Janissen
Author LinkedIn connections

Consent applicants under the Resource Management Act (RMA), territorial authorities and other RMA decision-makers will welcome the clarity of process provided by the High Court's ruling yesterday in relation to the Project Hayes wind farm.

The Court has ordered that the case be sent back to the same division of the Environment Court which declined the original resource consents and has imposed specific directions on how that Court will consider the matter, the effect of which is to return the Court's authority to the limits intended by the law.

High Court faults Environment Court's interpretation of the law

The Environment Court found that Project Hayes did not achieve sustainable management in terms of the RMA because the large quantity of renewable generation it would have delivered was not sufficient to outweigh the impact on the outstanding Lammermoor landscape.