An Auckland demolition contractor has suffered the consequences
of being unclear about price in its contract negotiations.
Auckland demolition company Demasol was subcontracted to
demolish a large concrete tank containing asbestos and submitted a
quote of $100,000 plus GST to the head contractor to complete the
work. In subsequent emails to the head contractor clarifying its
quote, Demasol confirmed "everything included at $100k"
but said it did not include costs to remove any asbestos that
Demasol could not see. In further email correspondence with the
head contractor, Demasol said its quote of $100,000 plus GST
covered "ALL removal" of asbestos. The head contractor
then issued a purchase order with Demasol's latest email
attached and work commenced.