ARTICLE · 25 JULY 2015

Contract interpretation – the pendulum swings back

This UK judgment had far-reaching ramifications for the interpretation of commercial contracts, including in New Zealand.

New ZealandCorporate/Commercial Law

A long-running dispute in a Welsh caravan park is the unlikely catalyst for a UK Supreme Court judgment that will have far-reaching ramifications for the interpretation of commercial contracts, including in New Zealand.

Arnold v Britton may mark a shift away from liberal recourse to a court's view of "business common sense" in contractual construction, in favour of a more traditional approach.

What price tidy lawns?

In dispute was a service charge for lawn mowing, rubbish removal and general site maintenance in 99-year leases of 25 chalets at a leisure park in South Wales.

The leases stated that the service charge would be £90 in the first year of the lease and that it would increase each year after that at a compound rate of 10% per annum. Assuming a lease granted in 1980, the 2015 service charge would be over £2,500 and, continuing on its skyward trajectory, would rocket up to £550,000 by the end of the lease – well in excess of any realistic estimate of