ARTICLE · 22 APRIL 2020

Construction contracts: Contractual framework for navigating through Covid-19 Alert Level 4 (NZS 3910:2013, NZS 3915:2013, NZS 3916:2013 & NZS 3902:2004)

Contractors who cannot complete due to COVID-19 need to take steps now to minimise risk of potential penalties.

New ZealandCoronavirus (COVID-19)
Craig Andrews
Craig Andrews

Parties to construction contracts, especially those contractors (and subcontractors) who are engaged to carry out particular contract works by an agreed due date for completion, may be exposed to penalties or "liquidated damages" if unable to carry on or complete those works during the Covid-19 Alert Level 4 lockdown.

Those contractors who are prevented from completing the contract works before the agreed date for completion as a result of the lockdown need to take prompt and accurate steps as contemplated under their construction contracts to seek suspension of the contract works or an extension of time for completion from the contract Principal (or the engineer where appropriate).

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from