In building permit cases administrative authorities that
fail to reach a decision on an objection within the statutory time
limit are by no means the exception. Authorities are particularly
likely to exceed the time limit by some considerable margin where
large construction projects require not only a building permit but
also a decision allowing an exemption from the zoning plan. Here
the time limits are six and ten weeks respectively (if an objection
committee has been set up).
As a notice of objection lodged against a building permit does
not in itself suspend the effect of the permit, a failure to take a
decision within the statutory period need not, in objective terms,
have any adverse consequences for the permit holder. As long as the
permit has not been suspended by way of interim injunction there is
no obstacle in a legal sense to the performance of the work. In
practical terms, however, the absence of a decision most certainly
has adverse consequences. Since