The effects of the recent Coronavirus outbreak have been
intensifying for the last couple of weeks, particularly following
the World Health Organisation's declaration that the virus is
now considered to be a global pandemic. Said effects are also
expected to reach a higher peak in the near future.
These effects have to date included a plunge in demand and
supply, various disputes and also contractual breakdowns. It also
implicates greater risks of disruption and business continuity
concerns. Furthermore, inability to perform certain obligations
might arise due to a number of restrictions.
An issue which is of particular importance with regard the
present epidemic is that of force majeure. A force
majeure clause excuses a party to a contract to carry out his
or her duties due to unforeseen circumstances. Whilst the
Coronavirus is most likely not to be referenced in a contract,
force majeure clauses typically include a list of events
such as government orders, wars,