Liquidated ascertained damages or
“LAD” are pre-agreed damages between
parties in the event of a breach of contract. It is meant to
compensate the innocent party for losses against the breaching
party. For instance:
1.1 Party A agreed to compensate Ringgit Malaysia Ten Thousand
(RM10,000.00) to Party B if Party A fails to deliver the property
within one (1) year;
1.2 By the end of that one (1) year, the property was not
delivered;
1.3 Party A is therefore entitled to the Ringgit Malaysia Ten
Thousand (RM10,000.00).
Section 75 of the Contracts Act 1950
(“CA 1950”) allows for such damages to
be claimed without the innocent party having to prove actual
damage:
“When a contract has been broken, if a sum is named in
the contract as the amount to be paid in case of such breach, or if
the contract contains any other stipulation by way of penalty, the
party complaining of the breach is entitled,
whether or not actual damage or loss is proved to have
been