Contract - Whether Right For Purchasers To Resile From Their Promise Not To Sue And Claim Damages For Late Delivery

The appellant ("Oxbridge") was a housing developer for a housing project ("the project").

MalaysiaCorporate/Commercial Law
Jayadeep Hari & Jamil
Jayadeep Hari & Jamil

CASE:

Oxbridge Height Sdn Bhd v Abdul Razak Mohd Yusof & Anor [2015] 3 MLRA 59

BRIEF FACTS:

  • The appellant ("Oxbridge") was a housing developer for a housing project ("the project").
  • The respondents ("the purchasers") purchased a unit from Oxbridge through a sale and purchase agreement ("SPA") dated 17 April 2006.
  • Clause 23 of the SPA required Oxbridge to deliver vacant possession to purchasers within 24 months from the date of the SPA.
  • Failing to follow Clause 23 would make Oxbridge liable to pay the purchasers liquidated and ascertained damages ("LAD").
  • Due to the flooding between December 2006 and early 2007, the project suffered financial difficulties and stalled.