Latvia plans to amend the regulation on natural resources tax (hereinafter – NRT), significantly changing its application to battery energy storage systems (hereinafter – BESS). The amendments provide for a reduction of the applicable NRT rate for the BESS, an extension of the exemption in respect of such projects and the removal of the existing exemption based on a supplier’s guarantee that end-of-life equipment will be returned to the supplier’s country.
What will change?
Under the regulation currently in force, an NRT payer who establishes a solar power plant for the purposes of carrying out its economic activity, with the total installed capacity of photovoltaic panels amounting to at least 1 MW, may be exempted from the payment of NRT on photovoltaic panels, inverters and electric accumulators for the accumulation of voltage produced by photovoltaic panels, provided that such NRT payer itself ensures the measures and covers the costs related to the waste management of the above