Superior Force Or Developer's Remorse? Justifiable Delay In Channel Island Construction Contracts

With seemingly ever-increasing costs of goods and materials, contractors and developers alike continue to feel the squeeze. Pressure on costs can only be compounded by...

JerseyReal Estate and Construction

With seemingly ever-increasing costs of goods and materials, contractors and developers alike continue to feel the squeeze. Pressure on costs can only be compounded by difficulties in securing delivery of goods and materials within a reasonable timeframe and indeed on time. Against a wider context of a challenging macro-economic environment, not to mention pandemic-related pressures, meeting pre-agreed development milestones is a growing challenge. But where does this leave contractors and developers who have committed to delivering a particular project on time?

Force majeure and extension of time

Contractual provision for justifiable delay or "force majeure" (French for "superior force") have long been a feature of the construction industry. They are typically agreed on relatively standard terms with those parties responsible for the timely delivery of a new development project. Such provisions represent crucial contractual protections for contractors and

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from