Contract Law Disputes Post-Covid-19: Force Majeure And Frustration In Hong Kong

Timothy Loh LLP
Timothy Loh LLP
Contributor
Timothy Loh LLP

Timothy Loh LLP

Timothy Loh LLP is a leading independent law firm based in Hong Kong. We practice corporate law and...

View firm profile
Explore more from Timothy Loh LLP

The initial impact of the coronavirus (Covid-19) pandemic disrupted supply chains as businesses along the chain were forced to close.

Hong KongCoronavirus (COVID-19)

The initial impact of the coronavirus (Covid-19) pandemic disrupted supply chains as businesses along the chain were forced to close. With infection numbers rising again and the prospect of new lockdowns and business closures on the horizon, in this article, we explore whether the pandemic may provide a basis under Hong Kong contract law for a party to that contract to argue that it should be excused from performing its obligations through the doctrine of frustration and force majeure (i.e. without triggering a contractual breach).

The coronavirus (Covid-19) pandemic has wrought significant damage to a Hong Kong economy already battered by political unrest and a reset in relations between the United States and the People's Republic of China. While the economy has now largely re-opened with virus numbers remaining low, the risk of further economic damage remains elevated as virus numbers in other parts of the world are now rising. In this environment, Hong Kong