Discain Project Services Ltd v Charles Le Quesne (Guernsey) Ltd

The Plaintiff sought to challenge the outcome of an adjudication proceeding between the two parties on the grounds that the decision was unfair and contrary to natural justice.

GuernseyWealth Management

The Plaintiff sought to challenge the outcome of an adjudication proceeding between the two parties on the grounds that the decision was unfair and contrary to natural justice. The Plaintiff alleged that the adjudicator failed to notify the parties of the substance of his decision or allow them to comment on it, and further failed to give reasons with respect to costs or awards. As a result, the Plaintiff sought to have the adjudicator's decision rendered void.

In supporting his position, the Plaintiff argued that the role of an adjudicator was similar to that of an arbitrator. The Court however considered the duties of the adjudicator with regard to costs, liability and quantum as distinct from the duties required by an arbitrator. The Court agreed with the judgment of Balfor Beatty Construction Ltd v Lambert London BC Macob [2002] EWHC 597 (TCC) that, while more generally the role of an adjudicator is similar to an arbitrator, they are not the same. The Court

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from