The introduction of Certificates of Lawful Use
("CLU")
Prior to May 2019 it was possible for unauthorised uses of land
or buildings in Guernsey to become immune from planning enforcement
action due to the passage of time. However, they could not be
recognised as lawful other than by way of a retrospective planning
application. For various reasons (including policy and case law),
such applications were frequently unsuccessful.
The island's Land Planning and Development (Certificates of
Lawful Use) Ordinance, 2019 introduced a route for property owners
to formally regularise any historic, unauthorised change of use of
land or buildings without needing to apply for planning
permission.