We are all now aware of the unprecedented obstacles that the
coronavirus has thrown up for the construction industry in just a
few months. The need for lockdowns and social distancing has
impacted almost every facet of the construction process, be it
supply chain manufacturing, the transportation of goods, materials,
workers, or the conduct of on-site operations. In this article, we
look at the impact on construction projects in East Africa and
analyse how parties can address the different risks caused by
COVID-19 such as force majeure and changes in legislation.
Background
As in many other regions around the world, East African
construction projects have been impacted by the coronavirus,
leading to programme delays and the suspension of projects. For
instance, construction works at Cytonn Investment's KSH 5
billion residential development, "The Alma" in
Nairobi, were suspended in order to lay down strict health and
safety measures to curb the spread of the