ARTICLE · 03 APRIL 2020

Force Majeure Event: The Example Of Supply And Delivery Contracts

August Debouzy
August Debouzy
Contributor
August Debouzy

August Debouzy

For the past 30 years, our law firm has been driven by an entrepreneurial passion, offering our...

View firm profile
Explore more from August Debouzy

As Covid-19 expands and Governments take increasingly restrictive measures, particularly with regard to borders,...

FranceCoronavirus (COVID-19)

As Covid-19 expands and Governments take increasingly restrictive measures, particularly with regard to borders, there are questions about the foreseeable consequences for supply and delivery contracts.

Indeed, the Covid-19 pandemic, by its suddenness and virulence, could in certain cases meet the three criteria of an event of force majeure defined in Article 1218 of the Civil Code: exteriority, unpredictability and irresistibility. If the analysis of previous decisions rendered in the context of other epidemic episodes (dengue fever, chikungunya, SARS) could lead one to believe that this qualification could be rejected, its recognition by judges could on the contrary be facilitated by the novelty and scale of the crisis, as well as exceptional restrictive measures been taken (see our article on this subject).

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from