The Court of Appeal of Helsinki has in its recent decision interpreted section 13 of the YSE 1983 general conditions for building contracts (concerning liability during the guarantee period.)

FinlandReal Estate and Construction
Risto Sipilä
Risto Sipilä

The Court of Appeal of Helsinki has in its recent decision interpreted section 13 of the YSE 1983 general conditions for building contracts (concerning liability during the guarantee period.) Section 13 of YSE 1983 is consistent with section 29 of the current YSE 1998 regarding the legal issue in question. The decision of the Court of Appeal is therefore applicable to the current YSE 1998 conditions. The decision of the Court of Appeal has legal force.

According to section 13  of YSE 1983 (and respectively section 29 of YSE 1998), the contractor is obliged at his own expense to repair any defects that emerge in his building work during the guarantee period, unless the contractor can demonstrate that the defects have occurred due to reasons beyond his control.