Planning In The Channel Islands - Time For 'Special Measures'?

Collas Crill
Collas Crill
Contributor
Collas Crill

Collas Crill

Firm Details: Chief Executive Officer: Jason Romer Managing Partners: Bermuda: Lilla Zuill, BVI:...

View firm profile
Explore more from Collas Crill

Eighteen English councils are at risk of having planning decisions taken out of their hands and dealt with by the Planning Inspectorate if they fall below specified thresholds under the ...

European UnionReal Estate and Construction

In this opinion piece, Senior Planning Consultant Chris Crew shares his views on some of the challenges faced by Guernsey and Jersey's States planning departments when it comes to performance.

Eighteen English councils are at risk of having planning decisions taken out of their hands and dealt with by the Planning Inspectorate if they fall below specified thresholds under the UK government's special measures programme, according to a recent Planning Resource article (subscription required).

Those thresholds are that 60% of major applications should be determined within the statutory deadline of 13 weeks, and 70% of non-major applications within eight-weeks.

Although not applicable in the Channel Islands, they serve as a useful comparator given that Guernsey and Jersey both set targets for speed of decision making under separate but similar statutory frameworks.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from