Share on LinkedInShare on LinkedIn

ARTICLE · 28 JANUARY 2014

Public Procurement: Taking Over Of The Obligations Of The Consortium Leader Is Not A Change Of Contractor

Schoenherr (Schönherr Rechtsanwälte)
Schoenherr (Schönherr Rechtsanwälte)
Contributor
Schoenherr (Schönherr Rechtsanwälte)

Schoenherr (Schönherr Rechtsanwälte)

Schoenherr is a leading European full-service law firm with a strong footprint across Central and...

View firm profile
Explore more from Schoenherr (Schönherr Rechtsanwälte)

The European Commission confirmed that a new public procurement procedure is not re-quired in order to take over of the obligations of the consortium leader (in insolvency) by way of enforcing a joint liability clause.

European UnionGovernment, Public Sector

The European Commission confirmed that a new public procurement procedure is not required in order to take over of the obligations of the consortium leader (in insolvency) by way of enforcing a joint liability clause.

Factual background

We were confronted recently with a need to identify solutions to allow continuation of a public procurement contract concluded with a consortium after the leader of the consortium entered insolvency proceedings and was no longer able to fulfil its contractual obligations. The judicial administrator decided that the consortium leader should withdraw from the consortium and the public procurement.

The public procurement contract included a clause for joint liability of members in consortium towards the contracting authority.