1. Ability of Parties to discharge their obligations under the
Contracts
a. Force Majeure
Both Gafta 64 and Gafta 100 are construed in accordance with
English law, under which parties' only recourse to Force
Majeure as a means of suspending and / or cancelling their
obligations is through the express incorporation of Force Majeure
wording. Such wording is present in both Contracts.
i. Event of Force Majeure
Under each Contract, Sellers (only) may suspend performance of
their obligations where their performance has been prevented
"whether partially or otherwise" by an "Event of
Force Majeure". In order to rely upon this wording, Sellers
will have to prove that the event falls within one of the twelve
definitions of "Event of Force Majeure" ((enumerated (a)
– (l)). It should be noted that some GAFTA standard form
contracts, e.g. Gafta 49, enable both Sellers and Buyers to suspend
performance, or where this is not the case, parties occasionally
amend the