All three electricity distributors in the Czech Republic have stopped accepting applications to reserve grid capacity from new photovoltaic and wind power plants.

Czech RepublicEnergy and Natural Resources
Helen Rodwell
Helen Rodwell
Lukáš Janíček
Lukáš Janíček

All three electricity distributors in the Czech Republic have stopped accepting applications to reserve grid capacity from new photovoltaic and wind power plants.

This does not affect power plants that have already reserved grid capacity.

This moves follows a warning by CEPS, the sole operator of the Czech electricity transmission system, that the system would become overloaded if the recent boom in the number of photovoltaic power and wind plants were to continue at its current pace.

It is not clear for how long new applications will be suspended. It is expected that they will start to be accepted again once the distributors have agreed stricter rules for reserving grid capacity. This could happen as soon as March.