The debtor paid various amounts between 31 May 1993 and 18 October 1999.

CyprusLitigation, Mediation & Arbitration

In a recent case, the Supreme Court upheld a lower-court judgment to dismiss an application under Order 40(8) of the Civil Procedural Rules requesting enforcement measures 18-and-a-half years after an initial judgment had been handed down.(1)

However, the appeal was dismissed on two grounds. First, the debt had not been established and second, there had been such a long delay in applying for the adoption of the enforcement measures.

Facts

On 31 May 1993 the appellants secured a judgment against the respondents (Action 679/1992), jointly and separately, for C£18,432 plus interest at 6% per annum and costs. This action concerned a car loan agreement. The first respondent was also ordered to hand over the vehicle in question to the appellants for sale by public auction.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from