May 2026 – After more than three years of regulatory limbo, the Croatian Energy Regulatory Agency (HERA) has replaced case-by-case "actual cost" pricing with a uniform EUR/kW tariff that applies across the country. Developers can again estimate connection charges at an early stage of the project development.
On 27 April 2026, HERA adopted the Decision on Unit Charges for Connection to the Electricity Grid (Cro. Odluka o iznosu jedinične naknade za priključenje na elektroenergetsku mrežu; the Decision), into force from 1 May 2026.
The Decision closes a regulatory gap that has held up the Croatian renewables pipeline since autumn 2022. Capacity-based connection charges now apply nationwide, replacing the project-specific, operator-led calculations of "actual costs" that varied by location and were difficult to model at the early stages of project development.