Six Takeaways From Construction Act Adjudication: Four Years In Review

McCarthy Tétrault
McCarthy Tétrault
Contributor
McCarthy Tétrault

McCarthy Tétrault

Built on a unique model of collaboration, innovation and efficiency, McCarthy Tétrault delivers...

View firm profile
Explore more from McCarthy Tétrault

On November 28, 2023, McCarthy Tétrault hosted a presentation reviewing the process, jurisdiction, timelines and procedures involved in Construction Act adjudication in Ontario.

CanadaReal Estate and Construction

On November 28, 2023, McCarthy Tétrault hosted a presentation reviewing the process, jurisdiction, timelines and procedures involved in Construction Act adjudication in Ontario. The presentation also covered risk management strategies to better prepare for adjudications' fast-moving timelines. Below are six key takeaways from the presentation.

1) Adjudication is meant to be "quick and informal". Organizations must be prepared to respond quickly to this fast-moving process.

Adjudication timelines are demanding. Once a Notice of Adjudication is delivered, the entire process is typically completed in six weeks or less.

  • The respondent has a mere four days to respond to the initial Notice of Adjudication.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from