ARTICLE · 28 NOVEMBER 2013

Off-Shore Wind Law Suit Against Ontario Will Proceed

Trillium Power Wind Corporation's planned off-shore wind farm in Lake Ontario was effectively cancelled by the provincial moratorium on off-shore wind development, openly adopted for political reasons.

CanadaEnvironment

Trillium Power Wind Corporation's planned off-shore  wind farm in Lake Ontario was effectively cancelled by the provincial moratorium on off-shore wind development, openly adopted for political reasons. Trillium sued the Province for $2.25 billion in costs thrown away and loss of profit, under numerous causes of action. As we  wrote earlier, the law suit was thrown out when the Province obtained a Rule 21 judgment, striking out the claim as disclosing no reasonable cause of action.  Trillium appealed, and can now proceed to trial on the basis of one of its causes of action: misfeasance by the provincial government in public office.

In a decision released on November 12, the Court of Appeal continued to dismiss most of Trillium's claims. It was "plain and obvious, and beyond all reasonable doubt, that the appellant could not succeed in its claims for breach of contract, unjust enrichment, taking without compensation, negligent misrepresentation and negligence, and

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from