In the past, you have likely entered into a contract that
contained a liquidated damages clause. These are prevalent in
construction and general commercial agreements.
Liquidated damages and penalty clauses
Liquidated damages (or stipulated damages) clauses are estimates
made at the time the contract is formed of the expected losses a
party will suffer in the event of a breach of the contract.
Traditionally, these clauses are enforced as long as they represent
a genuine attempt to pre-estimate the loss. 1
Where such a clause is deemed not to be a genuine pre-estimate
but is rather a sum that is "extravagant and unconscionable in
amount in comparison with the greatest loss that could conceivably
be proved to have followed from the breach," the clause will
be considered an unenforceable "penalty
clause."2 These are clauses which are
essentially designed to deter a party from breaking a contract,
irrespective of the anticipated loss.