The perils of not providing body corporate disclosure statements in time, before settlement

The purchaser of a unit can cancel the agreement if the disclosure statements are not provided within prescribed times.

New ZealandReal Estate and Construction

A vendor of a unit needs to be aware of the requirement to provide:

  • a pre-contract disclosure statement before the purchaser enters into an agreement;
  • an additional disclosure statement, if requested by the purchaser, no later than five working days after it is requested; and
  • a pre-settlement disclosure statement, at least five working days before the settlement date.

Vendors should be made aware of the perilous consequences of failing to provide a pre-settlement disclosure statement or an additional disclosure statement in time. If these statements are not provided in time, the purchaser has two options:

  • postpone settlement to the fifth working day after the date on which the latest disclosure statement was given; or